The AMP Centre in the historic Circular Quay precinct has used Thermospray 800 insulation from Enviro Acoustics in its refurbishment.

Progressively from 2002, the building has been refurbished and a special requirement was to install a thermal barrier behind the exterior façade. This insulation had to be completely, as offices were to be occupied during the process. Thermospray 800 fully approved injected insulation offered a guarantee of 100% remote filling to ensure no "hot spots".

The injection of the Thermospray 800 insulation is a clean and safe process with minimum waste. In addition, it is made of recycled materials.

Project features:

  • 43 Levels
  • Jacket Area is 280 m² per level
  • Spandrel Cavity is 100 mm
  • Thermal Conductivity is 0.034W/mK
  • Time for Completion was 3 days per level